We often assign sprints by manually selecting them from the drop-down in the right pane of a card.
Recently, the contents of the drop-down changed in an unexpected manner.
Previously, as we clicked in the field, it would show something like:
Dev Sprint 120
current
Dev Sprint 121
future
and so on.
Now, we find:
Dev Sprint 120
current
Dev Sprint 120
future
Dev Sprint 121
future
We could ignore it, but not all views offer the current vs future distinction label.
Help?
Pretty sure I can answer my own question.
Two projects display on the board we use for a combined sprint, but they are each scrum in and of themselves and some sprints were accidentally created in one of the individual projects as well as in the shared scrum board. Removing the sprints created in the backlog of the individual project solved the issue.
Hi @Alex Romano
Would you please mark your own question as answered? That will help others in the community find solutions faster if they see the same symptom. Thanks!
__Bill
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.