I cannot complete the sprint, because warning says i have 17 open issues, but i have already mark that 17 issues with status that mark the resolution to "done"
17 open issues, but i have all resolution to "done"
Filter only "task" and "story" within sprint-3, a total of 17 issue
Filter for all Sub-task within that "story" and sprint-3 , but for the total of sub-task is 57, no match for 41 completed issue or even 17 open issues.
i just tested add another issue on backlog without attach it to sprint-3, and i change the status from to-do to RC Deployment, when status in to-do. the "complete" sprint from sprint-3 still only have 41 complete issue. but then after i change status to rc deployment, the "complete" screen page from sprint-3 change to 42 complete issues.
so the sprint 3 complete issues too acting funny because it may look-like related to issues on backlog
Hi @Andrew and welcome to the Community!
Jira considers issues in a sprint to be open as long as they are not in the rightmost column of your board. That is most likely what is happening here. Status or resolution don't matter here, just have a look where the issues are on the board and have a look in your board settings how you have mapped statuses to columns.
Hope this helps!
thank you for the response, for the rightmost column did you mean this column "done",
to make all issue is completed, i need to place it on done column right?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
For issues to be considered complete in this board, yes - that is the column they should be in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
i have other question, recently are there an updates version on Jira side regarding the complete sprint requirement?
because on my last sprint (sprint 1 and 2) my issues are not on "Done" column, but i still can complete the sprint
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.