The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Report

Richi Prathama
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 9, 2014

Hi,

I am using a JIRA with Kanban, the question is can I make a report that can gather a weekly report for time consuming at all the ticket status individually per developer. And download it to csv.

A custom report will be great so the HRD or someone that doesnt know about JIRA can understand how much work that developer have per day or week.

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
AgentSmith
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
January 16, 2015

I believe that would be the cycle time, which is reflected in the Control Chart report but not sure if it'll filter by assignee. 

The Control Chart can show the cycle time (or lead time) for your product, version or sprint. It takes the time spent by each issue in a particular status (or statuses), and maps it over a specified period of time. The average, rolling average and standard deviation for this data is shown.

Reference materials:

https://confluence.atlassian.com/display/AGILE/Viewing+the+Control+Chart

https://confluence.atlassian.com/display/AGILE/Cycle+Time

 