I created a new workflow with a new status "My Status Done". I created this new status with category "Done".
All jira issues with this new status are shown as "Done" and the Story Points of these issues with the new status are added in "Done - Story Points" in the Sprint bar.
When I want to complete the Sprint, Jira shows me a message that said: "This sprint contains: 0 completed issues, 6 open issues"
Could someone tell me please what I have to do to get this issues complete?
Thanks in advance!
Welcome to the Atlassian Community!
My guess is that your new status is not in the last column on the board. That's all Jira uses to determine whether an issue is done or not.
Thank you! It works! I really appreciate your response.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.