Hi All,
I have a program created on Biggantt and I have grouped few tasks under the parent tasks.
[Scenario1] If I link child tasks to one another across the different parents, then Biggant automatically takes care of the Weekend holiday setting and makes sure that tasks follow the setting.
[Scenario1] If I link child tasks to parents, then Biggant automatically takes care of the Weekend holiday setting and makes sure that tasks follow the setting.
[Scenario 3] However, if I link two parent grouped ones, then it doesn't consider Weekend setting at all.
Need to understand why this is happening.
(Refer Attachment)
Thanks in advance