Jira in a new Resolved state shown as resolved yet carried forward to next sprint

Gilbert Louis March 4, 2019

Hi,

I've clearly done something wrong somewhere but don't know where... I Created a new resolved JIRA state (show showing in green) and updated our workflow to we can move jirato that new state. 

All good in the sprint... but when I closed our sprint, all the jira in that new state didn't get released and were carried forward onto the new sprint ???

Writly or not I though jira moved to a resolved state are considered 'done' and so would not carry to the next sprint and will show as part of the release.

Basically I added an intermediate state when a jira is completed but not release I called 'Done. Waiting to be merged'. So they are sitting in their branch but not merged to the master in our live system yet. This is so we can test each of the independently to start with. And these are part of an Epic which will take 2 or 3 sprints to complete.

I created that state as I didn't want these tasks to 'pollute' the new sprint as they were done and no activity will be done on these so they would count for the burndown and for the velocity as done for that sprint which would be correct. While also keep track of all these jira so as the time comes to merge we know where to find them all.

Before I switch to the new sprints we had 4 jira in that new state. When I closed the sprint they got moved to the new sprint, to my surprised. I thought they'd considered as resolved and so removed from the sprint to be released.

Any idea what I've done wrong?

1 answer

1 vote
Claudiu Lionte
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
March 4, 2019

Hi Gilbert,

The new status needs to be mapped to the rightmost column of the board. Please go to board settings -> columns and drag&drop this new status to the rightmost column. You will have to leave the Done status there as well (there can be multiple statuses in the same column).

Claudiu

Gilbert Louis March 5, 2019

Hi @Claudiu Lionte  thank you for your response. Currently Done. Waiting to be merged column is on the left side of the done column (2nd most right column).

Are you saying I have to 'merge' these 2 jira states into the Done column of the board? Ideally I'd like to keep them separate if possible.

If so does this mean that JIRA only take jiras from that far right column of the board for release not all jira in any state of resolved?

 

Gilbert

Claudiu Lionte
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
March 6, 2019

Hi Gilbert,

Yes. A board in Jira (software) considers as Done only the issues in the rightmost column.

If your workflow has multiple statuses that are final, all of them should be mapped to the rightmost column (or you can not map all of them and leave some un-mapped).

Suggest an answer