Hi all,
Hi @Pooja
Guess the date format in the jira import is dd/mmm/yy h:mm.Try changing the format to dd/mm/yy and import it should import your csv file.
or import the value as dd/mmm/yy h:mm (eg: 15/jan/18 01:22 )
Cheers,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Your date should look like this:
22/Oct/18
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Welcome to great meetings, with less work. Automatically record, summarize, and share instant recaps of your meetings with Loom AI.
Learn moreOnline forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.