Is it possible to select all issues with timespent > timeoriginalestimate via advanced searching?

Christian Groth August 21, 2012

In the documentation for the advanced-search there is only an example for timespent-search where tmespent is compared with an amount ot hours (e.g. 5h). Is it possible tgo slect all issues with timespent > timeoriginalestimate?

3 answers

1 accepted

11 votes
Answer accepted
Alex Taylor
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 21, 2012

Seach for 'workRatio > 100'. That will return all issues whose timespent is greater than the original estimate.

Christian Groth August 21, 2012

Allex, thanks for your hint!

Art B
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 17, 2017

I am looking to query tasks which have Remaining greater than Estimated. WorkRatio >100 only retursn items where Logged > Estimated. How can I find task that our Remaining > Estimated?

 

Thanks

Like • 4 people like this
Aditi Mishra
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 29, 2023

Very helpful

Parisa Khoshniat
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 11, 2023

this really work. Thank you 

0 votes
Art B
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 17, 2017

I am looking to query tasks which have Remaining greater than Estimated. WorkRatio >100 only retursn items where Logged > Estimated. How can I find task that our Remaining > Estimated?

0 votes
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 21, 2012
Christian Groth August 21, 2012

Hi Jobin,

thanks for your answer.

I tried a very simple search: timeestimate < timespent

But this didn't work, Jira prompted the error-message

The value 'timespent' for field 'timeestimate' is invalid. Please specify a positive duration format; for example: '1h 30m', '2d'.I giot the g

In the documentation there is only an example where timespent is compared to a specific value (e.g. 5h).

Do you have another hint for me?

Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 21, 2012

I asked you to search using workRatio. Did you read the doc?

Christian Groth August 21, 2012

Sorry, I should have read your first answer more carefully! With using the workratio it works fine!

Thanks.