Is it possible to automatically "start progress" of an issue after assign it?

Hi everyone!

I would like to automatically set the action "start progress" after someone assigns an issue. Is it possible?

Do I have to change the Default Workflow to do this?

Thanks!

1 answer

1 accepted

1 votes

No. Assigning an issue is an action outside the workflow.

Although you could move some of it into the workflow and get some flexibility there, you'd still have the "assign issue" options available in the general actions

If you were not using OnDemand, you could use the "auto-transition listener" - that can catch "assign" events and push issues through the workflow.

Thanks Nic Brough! Actually, I'm using the OnDemand version. I've found a way to do it creating a new workflow. I created a "post condition" that automatically assign the issue to him when the progress is started. So, I changed the way to start the treatment of my issues.

Thanks one more time!

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

3,116 views 13 19
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot