Is it possible to associate a sub-task type with a specific issue type?

Boris Volpe October 4, 2013

I have a sub-task type that is scpecific only for issues of type 'Bug'. I want to be able to allow selecting this sub-task type only when parent issue is of type 'Bug'. Is this possible to do and, if yes, then how it can be done?

1 answer

1 accepted

0 votes
Answer accepted
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 4, 2013

You can't do this. If your project only needs on subtask type, you can create an issue type scheme that only has that subtask type and that will work.

Boris Volpe October 7, 2013

Thank you Jobin. I expected that this is not possible. I do not think that creating an issue scheme will solve my problem becasue it does not address ability to limit subtask to a specific issue type.