Is it possible to assign a workload plan to a resource per project?

Morgan Bourree December 15, 2021

Hello,

I am looking for this possibility of assigning a workload plan to a resource per project, is it available?

If not, is there a workaround?

I really need it to specify for instance that a developer is working 40% on project A and 60% on project B.

Thanks,

Best Regards

2 answers

2 votes
Nataliya Vasyliv_Reliex_
Atlassian Partner
December 21, 2021

Hi @Morgan Bourree 

I'm Nataliya from ActivityTimeline team. ActivityTimeline could support your use case. 
ActivityTimeline add-on allows creating a reservation for a potential work in the future. You can fill in the project and defines how many hours (or in percentage) should be booked for a person.  
Booking_ActivityTimeline.png
If you have any additional questions please feel free to ask me. We can provide a demo session for you if needed. 

I hope you find it helpful.

0 votes
Anna-BigPicture
Atlassian Partner
December 29, 2021

Hi @Morgan Bourree

Hello, If you consider using an additional plugin, BigPicture can provide you with a solution. Apart from supporting project planning and tracking, the app facilitates distributing workload and allocating resources.
You can define a developer availability per project assigning 40% of capacity to a team working on project A and 60% to a team working on project B.

Let me know if you have further questions.