I do not see any story points in committed and completed in velocity chart

Amit.Goyal August 25, 2021

I have completed 3 sprints so far but I donot to see any story points in committed and completed in velocity chart

 

 

1 answer

0 votes
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 25, 2021

Hi @Amit.Goyal -- Welcome to the Atlassian Community!

First thing, are you using a company-managed project or a team-managed project?  You can determine this by looking at the bottom of the left-sidebar menu.

Next, please look over this documentation for the velocity chart and then review:

  • What is your estimation statistic set to?
  • The "committed" values only show issues in the sprint when it was started.  Were your issues in the sprint *and* sized with story points when the sprint started?
  • The "completed" values only show issues in the right-most column of the board when the sprint completed, and so "done".  Have you check your board set up and the status of those issues?

Best regards,
Bill