Hi
in the Timeline view it allows you to create an item but only lets you create 1 sub level from that item but does not allow you to create further sub levels
for example the Timeline view would look like as follows
How do i create a the Sub item 2 as shown above in the timeline view?
thanks for your help
Hi @John and welcome to the Community!
The timeline view currently does not support the sub-task level of the hierarchy. This is a known limitation with a suggestion to add this that you can track here: JSWCLOUD-18677.
As workarounds, the hierarchy from Epic > Task > Sub-task is visible in the list view or - if you are on a premium plan - can be displayed in an advanced roadmaps plan.
Hope this helps!
That's great thanks for your help
I hope they can implement this fix as soon as possible as without being able to include further sub item levels within the timeline view does make it very limited for a project management software