I am using next gen project>scrum>board. I've to created following columns on the board:
When the last three are chosen - Cancelled/Not a bug/prod release, I want these columns to be considered as "done". How do I achieve this?
Why have you set up swimlanes that mirror your columns? This gives you a board with a single diagonal line of filled cells and renders all the wasted space useless.
Jira Software considers only the last column on a board as "done", so the only good way to consider multiple "done" status is to put them all in the last column.
Hi Nic, sorry, I wrote it wrong. I've created columns, not swimlanes. And I need multiple columns as done.
Would a better approach be to use multiple swimlanes for the things below instead of columns?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can set up swimlanes for those three status, but they will have nothing to do with "done" - that is determined by columns.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.