You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Project type: Company-managed
Issue types: Epic, Story, Chore, Bug
Context:
Problem:
Screenshot:
Hi @Nik Jordanov,
I suspect that the estimation statistic of your board is set to story points. Most likely, the story points field is available on your Chore issue type.
If this is a company managed project, you may want to check the context of the Story Points custom field and - if it is available for Chores, remove it from the scope.
To do so, navigate to Jira Settings > Issues > Custom fields and look for the Story Points field:
Click on the link that says 1 context (that may be different in your Jira instance) and check if you can see other issue types than story listed there:
If Chore is there, click Create, edit or delete contexts and in the next screen click Edit Configuration and make sure to unselect Chore from the list of issue types using the field. Save your changes and head back to your board backlog view.
Hope this helps!
I had removed the field from the Screen but not from the Context - your suggestion worked! Thanks very much!