Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,551,938
Community Members
 
Community Events
184
Community Groups

How to remove an IssueType from the estimatable issues?

Project type: Company-managed

Issue types: Epic, Story, Chore, Bug

Context:

  • Currently, in the "Backlog" of my board, I see everything apart from Epic
  • Issues of type "Bug" don't have a visual icon for estimate or lack of estimate "-" (the one that's summed up on top of Sprints / Backlog)
  • Issues of type "Story" & "Chore" however, do.

Problem:

  • I want to change "Chore" so that any issue with that type behaves like "Bug", i.e. doesn't show it's waiting for an estimate. Where do I do it?
    • I've removed the "Story points" field from the "Chore" screen on which the estimation for the board relies but to no avail.

Screenshot:

Story-Bug-Chore.png

1 answer

1 accepted

1 vote
Answer accepted
Walter Buggenhout _ACA IT_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Apr 06, 2023

Hi @Nik Jordanov,

I suspect that the estimation statistic of your board is set to story points. Most likely, the story points field is available on your Chore issue type.

If this is a company managed project, you may want to check the context of the Story Points custom field and - if it is available for Chores, remove it from the scope.

To do so, navigate to Jira Settings > Issues > Custom fields and look for the Story Points field:

Screenshot 2023-04-06 at 17.36.17.png

Click on the link that says 1 context (that may be different in your Jira instance) and check if you can see other issue types than story listed there:

Screenshot 2023-04-06 at 17.37.42.png

 

If Chore is there, click Create, edit or delete contexts and in the next screen click Edit Configuration and make sure to unselect Chore from the list of issue types using the field. Save your changes and head back to your board backlog view.

Hope this helps!

I had removed the field from the Screen but not from the Context - your suggestion worked! Thanks very much!