How to make the Control Chart display data for a sprint?

Jan Tietjens Mar 14, 2013

I am currently evaluating JIRA (v5.2.6#849-sha1:560c048) with Greenhoper (v6.1.3.2) and wondering how I could get the Control Chart to display data in the Scrum modus?

Currently this report did not show any data at all in the Scrum mode, the Kanban mode works as expected.

1 answer

0 votes
Chin Kim Loong Atlassian Team Mar 27, 2013

Hi Jan,

I assume you will understand how to show the data in Control Chart by referring the document below:

https://confluence.atlassian.com/display/GH/Viewing+the+Control+Chart#ViewingtheControlChart-Daterange

Hope it helps

Jan Tietjens Mar 27, 2013

Hi John, unfortunatly the control chart did not view any data in the Scrum mode. I tried to adapt the date range but nothing happens. As I said before in the Kanban mode this works as expected.

Suggest an answer

Log in or Sign up to answer
This widget could not be displayed.
This widget could not be displayed.
Community showcase
Published in Jira Software

Early Access: If you use Jenkins and Jira Software Cloud, you need to read this!

The Jira Software Cloud Team has been busy working on a simple, secure, and reliable way to integrate your build and deployment information from Jenkins with Jira Software Cloud. This means you don’t...

280 views 0 8
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you