How to make the Control Chart display data for a sprint?

I am currently evaluating JIRA (v5.2.6#849-sha1:560c048) with Greenhoper (v6.1.3.2) and wondering how I could get the Control Chart to display data in the Scrum modus?

Currently this report did not show any data at all in the Scrum mode, the Kanban mode works as expected.

1 answer

0 votes

Hi Jan,

I assume you will understand how to show the data in Control Chart by referring the document below:

https://confluence.atlassian.com/display/GH/Viewing+the+Control+Chart#ViewingtheControlChart-Daterange

Hope it helps

Hi John, unfortunatly the control chart did not view any data in the Scrum mode. I tried to adapt the date range but nothing happens. As I said before in the Kanban mode this works as expected.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 18, 2018 in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

25,503 views 2 7
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you