How to define start/end-dates of sprints in advance?

Hello,

I want to create sprints in advance for the next 6 months and would like to enter their start- and end-date.

1) How can I achieve this?

2) Is there an overview like a roadmap with the planned sprints (and eventually already planned User-Stories for these sprints?) so that I can show my stakeholders when which feature is being developed?

Thanks,

Thomas

1 answer

I do not think you can plan multiple sprints in advance. JIRA Agile lets you plan the start and end date of the current sprint only.

I understand your requirement, so what you can do is assign versions to all your user stories and you can set a release date on your version which can be used for reporting purposes on when a story is planned to be developed.

In the newer jira agile version (6.2), you can manage versions directly from the jira agile boards.

Have a look at this URL

https://confluence.atlassian.com/display/AGILE/GreenHopper+6.2+Release+Notes

Rahul

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Jan 08, 2019 in Jira

How to Jira for designers

I’m a designer on the Jira team. For a long time, I’ve fielded questions from other designers about how they should be using Jira Software with their design team. I’ve also heard feedback from other ...

1,052 views 4 9
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you