Hello,
I want to create sprints in advance for the next 6 months and would like to enter their start- and end-date.
1) How can I achieve this?
2) Is there an overview like a roadmap with the planned sprints (and eventually already planned User-Stories for these sprints?) so that I can show my stakeholders when which feature is being developed?
Thanks,
Thomas
I do not think you can plan multiple sprints in advance. JIRA Agile lets you plan the start and end date of the current sprint only.
I understand your requirement, so what you can do is assign versions to all your user stories and you can set a release date on your version which can be used for reporting purposes on when a story is planned to be developed.
In the newer jira agile version (6.2), you can manage versions directly from the jira agile boards.
Have a look at this URL
https://confluence.atlassian.com/display/AGILE/GreenHopper+6.2+Release+Notes
Rahul