I've been trying to create a scheduled recurring action to do the following:
A few different configurations have been tested, introducing steps to create a new issue, refresh issue data, etc. I suspect my issue is related to the required JQL query associated with the scheduling trigger. Currently, the JQL is issuekey=[destination epic]
So far, I've achieved:
Missing:
Could someone help me understand what I'm missing here? Thank you!
Hi @Carina Lora -- Welcome to the Atlassian Community!
I am a bit confused by your use case, as your description seems different from your example rule. It seems like you want to:
Is this correct? If so, your rule could be:
This will work for a company-managed project. If you are instead using a team-managed project then epic/story are linked using "parent" instead of "epic link".
Kind regards,
Bill
Hi Bill! Thank you so much for the prompt and helpful reply. I was missing the checked box in the trigger JQL and had a refresh step in place instead. Digging through support answers got me somewhere, just not quite where I needed to go.
Your suggestion worked exactly as needed. Thanks again!