Hello,

I have an issue with the remaining estimate tab. Basically I can not change the remaining estimate from the plan view for user stories with subtasks.

When i click edit the remaining tab doesn't appear. Only when creating issues this tab is available.

Although when looking at a story and its subtask, next to the status you see the remaining estimate but that cannot be changed. Just the original estimation can be changed.

How can I change remaining estimates?

Thank you,

Silviu.

2 answers

Silviu,

Could you check your screen scheme for your sub tasks. It could be that the fields you need are only present on the create and view screen and not on the edit screen.

take a look here for more information:

https://confluence.atlassian.com/display/JIRA/Associating+a+Screen+with+an+Issue+Operation

Best regards,

Peter

Hello,

I don't see any screen besides the default screen scheme. And the "remaining" field is not available in the select field tab from the configure screen view.

Thank you,

Silviu.

Hello,

I don't see any screen besides the default screen scheme. And the "remaining" field is not available in the select field tab from the configure screen view.

Thank you,

Silviu.

Suggest an answer

Log in or Sign up to answer
TAGS

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you