Hi all,

I wanted to change/transfer the Sprint of our cards; for example XYZ Sprint 3 to XYZ Sprint 4. I tried doing a bulk change. On step 3 of 4 of the bulk change process, I can see the field Sprint - (and I know the sprint is represented by numeric). However there is no option to input the Sprint number, except a note that says "Inherited from parent".

And in step 4 of 4 of bulk change, the confirmation page displays the new Field Value as blank because I was not able to specify which Sprint in step 3.

How can I bulk move cards from one sprint to another?

I have attached screenshots for your reference.

bulkchangesprint.jpg

Thanks.

1 answer

1 accepted

2 votes
Answer accepted
Zaldy Parian
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 2, 2021

I found the answer to my question. And here's how....

In the JQL, include a criteria for "AND issuetype in (Epic, Story, Task)". After that, do the bulk change. 

In step 3 of 4 of the process, assign the new sprint number.

 

Hope this help anyone who will have the same issue as mine.