Hi all,
I wanted to change/transfer the Sprint of our cards; for example XYZ Sprint 3 to XYZ Sprint 4. I tried doing a bulk change. On step 3 of 4 of the bulk change process, I can see the field Sprint - (and I know the sprint is represented by numeric). However there is no option to input the Sprint number, except a note that says "Inherited from parent".
And in step 4 of 4 of bulk change, the confirmation page displays the new Field Value as blank because I was not able to specify which Sprint in step 3.
How can I bulk move cards from one sprint to another?
I have attached screenshots for your reference.
Thanks.
I found the answer to my question. And here's how....
In the JQL, include a criteria for "AND issuetype in (Epic, Story, Task)". After that, do the bulk change.
In step 3 of 4 of the process, assign the new sprint number.
Hope this help anyone who will have the same issue as mine.