I want to migrate approx 5000 Bug list from FogBugz to Jira. Before I start the migration project; I want to estimate the time and effort.
This does depend on a few things such as:
^ You need to know what data you want to migrate and into what structure in Jira - as the two platforms do vary.
Based on the above it could be a matter of hours right up to a few days I would imagine. But if it was a simple export / import with all completed mapping it could be done pretty quick :)
Ste
There is effort and duration. Effort might be 1-2d but duration maybe 5d. The duration considers trial and error, designing projects, clean up, etc. getting the issues imported would only be a few hours. My point here is to plan for a week to go live.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you so much Ste and Jack! This helps me to have some timelines planned. I will write to you once I have a definite approach to migrate these instances. Thanks once again!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.