How do I create an S Curve report?

Graham Crowe
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 4, 2019

I need to create an S-Curve report out of JIRA to show the project's progress over time to date. Basically, I need a graph with the horizontal axis being time (starting from the project start date, ending at the current date) and the vertical axis being % complete.

The curve would then have a point plotted for every week with the height being calculated as "total hours of work done / total hours of work estimated". Hours of work done would be based on work logged (or if no work logged for a particular task where the task is marked "done" then use the estimated time for that task).

I need to plot multiple curves (a different curve for different issue types)

Note that the projects I will run this on are populated with all JIRA tasks prior to any work starting, and are complete once all JIRA tasks are closed (this is not an ongoing support scenario)

Is it possible to generate such a report?

How would I go about doing it?

Thanks

2 answers

0 votes
Yossi barezer
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 18, 2024

who can answer this?

0 votes
firlian
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 29, 2019

same question, pls anyone help.

Suggest an answer

Log in or Sign up to answer