How can I update the configuration of a Burdown Chart?

EL ASSALI Meryam April 19, 2023

Hello, 

 

I would like to make my burdown chart based on the status "Test Ok" but not the status "Done". 

 

How can I proceed? 

 

Thank you

1 answer

1 vote
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 19, 2023

Welcome to the Atlassian Community!

Reconfigure the board the burndown chart belongs to.  Put "Test ok" in the very last (rightmost) column on the board.  Then make sure "done" is in a column before "test ok"