How can I see % completion of work on each story based on hours logged by users

Shailaja_Tadla December 19, 2022

Hello Team

 

Is there a possibility to view the percentage of completion of work on each user story or task based on the worked hours logged by each user. I have been asked for this report by my superiors. Please advise

 

Thanks.

Shailaja Tadla

2 answers

2 accepted

3 votes
Answer accepted
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
December 19, 2022

Hello @Shailaja_Tadla 

The Work Ratio field will show you the percentage of time logged comparing Time Spent to Original Estimate. If you have multiple people logging time against a single issue it won't show you values per user, but rather just overall for the issue.

Screen Shot 2022-12-19 at 11.52.48 AM.png

 

In a Company Managed project you can also add the Work Ratio field to Card Layout to show it on each card.

Screen Shot 2022-12-19 at 11.55.15 AM.png

Shailaja_Tadla December 21, 2022

Thank you so much Trudy

Shailaja_Tadla December 21, 2022

This was really helpful

Dave Mathijs
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
December 21, 2022

Thanks @Trudy Claspill for reminding me of the Work Ratio field!

Like Trudy Claspill likes this
Saurabh Kejriwal January 18, 2024

That helped. thanks a lot @Trudy Claspill .

0 votes
Answer accepted
Dave Mathijs
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
December 19, 2022

HI @Shailaja_Tadla If you add an Original Estimate to you issue, then original estimate - time spent = remaining estimate. This is not displayed in percentage, but in days/hours.

Third-party apps may feature the progress in percentage based on hours, not based on resolution.