Hello Team
Is there a possibility to view the percentage of completion of work on each user story or task based on the worked hours logged by each user. I have been asked for this report by my superiors. Please advise
Thanks.
Shailaja Tadla
Hello @Shailaja_Tadla
The Work Ratio field will show you the percentage of time logged comparing Time Spent to Original Estimate. If you have multiple people logging time against a single issue it won't show you values per user, but rather just overall for the issue.
In a Company Managed project you can also add the Work Ratio field to Card Layout to show it on each card.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks @Trudy Claspill for reminding me of the Work Ratio field!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI @Shailaja_Tadla If you add an Original Estimate to you issue, then original estimate - time spent = remaining estimate. This is not displayed in percentage, but in days/hours.
Third-party apps may feature the progress in percentage based on hours, not based on resolution.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.