How can I add a sprint to a version?

We have recently switch to using Jira agile. After switching to scrum boards and using sprints there doesn't seem to be a way to say that release 2 includes sprint 4 and 5.

2 answers

Hi Julie

I would first want to question why you would want to do that. A sprint is a collection of stories that you ideally want to complete in a fixed period of time. It is not necessary that you will complete your sprint fully and that is exactly why we measure velocity.

If you had the option of adding all issues in sprints directly to fix versions then there would be a risk of adding an unfixed issue in the sprint to a release which is not ideal.

If you are sure that all issues in your sprint are fixed and ready for release what i suggest you is use JQL to search for the sprint and then do a bulk change to modify the fix version of all the issues returned from the search.

Hope this helps.

Rahul

You could also - in Scrum|PlanBoard - drag and drop the issues to the right fixVersion.

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Thursday in Jira

Meet the AUG leaders of Northern Virginia

@Rachel Wright (Jira Genie), @Billy Poggi (AUG NOVA, DC), and @Dana Jansen (Confluence Queen) are just some of the folks that lead one of the world's most active Atlassian User Group (AUG)....

125 views 4 9
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you