After adding tasks in Jira and creating sub-tasks for them, an issue arises when trying to link a sub-task to another recently created task. This issue occurs frequently across all my products. For example, I created Task 117982 at 4:00 PM and another task at 7:00 PM then created task are automatic link to the another task.
Welcome to the community.
What is you exact request to the community?
If it is about Sub-task form a Task linking to another Task, this is not possible. Sub-Task have a single parent.
You can move a Sub-Task to a new parent or convert it to an issue (make it a Task or Story or Bug)