Estimate change when sub-task changes

We work with task and subtasks. We set the Estimates hours on the task and log our hours ion the sub-task. When a sub-task has no estimate itself and hours are written, the hours are added to that Estimate of the task where it belongs to. Can we prevent that the estimated hours of the main task will be changed writing hours on sub-tasks which have no estimate?

1 answer

The parent task estimated hours will be the sum of all estimated hours for each sub task. When you log work against sub-tasks, your parent issue remaining estimate is automatically adjusted.

So if you want to exclude sub-tasks work hours from parent then, In the estimate section of the display, there is an option to toggle between "all" and "parent only" display. Try it.

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

2,755 views 11 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot