Customized availability calendars for each resource WBS Gantt Chart

Andrea Fontanini December 5, 2022

Hi, I use WBS Gantt Chart and I have a question about resources. Is it possible to create customized availability calendars for each resource? And, if so, do these calendars interact with scheduling? 

Let's suppose to have a task A which has a duration of 4 days and to have a resource R that works only on Monday, Wednesday and Friday. We assign task A to resource R. Does the app automatically schedule the task end date knowing this informatio (so if I start on Monday, this task will finishin on the following Monday, i.e. 4 working days for our resource A)?

Thank you!

1 answer

1 accepted

0 votes
Answer accepted
Alessandro Portela Cristiano
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 6, 2022

Hello @Andrea Fontanini ,

Appreciate you sharing your use case.

We are gathering interest from our customers for this feature in the following Productboard card:https://portal.productboard.com/ricksoft-inc/5-wbs-gantt-chart-for-jira-cloud/c/256-add-specific-user-private-holiday-to-calendar 

Please access the Productboard card link sent above to cast your vote for it by clicking NICE-TO-HAVE, IMPORTANT, or CRITICAL. To be notified if it becomes available, enter your Email address, and then Submit.

We'll be looking forward to hearing your thoughts on this matter. Please let us know if you need assistance with the WBS Gantt Chart for Jira or have any other questions. It will be our pleasure to help.

We wish you a great day!

Kind Regards,
Alessandro C. | Support Engineer
Ricksoft Support Team

Andrea Fontanini December 6, 2022

Ok, thank you @Alessandro Portela Cristiano 

I hope this feature will be available soon!

Kind Regards.