Copying custom field contents to standard fields as part of workflow

We have set up a JIRA project and workflow to manage requirements capture and assignment to a release.

In order to ensure clarity for the users the requirements project has a custom field called 'User Story'. Once the requirement has been assigned to a release we want to transfer the requirement over to the relevant delivery project where it will become an issue but we want to copy the 'user story' field contents into the 'description' field.

Can this be done?

1 answer

1 accepted

Accepted Answer
4 votes

You can accomplish this by adding a post function to the relevant workflow transition. The specific post function you want to use is "Copy Value from Field to Field".

I haven't tested it myself, but I think this will ADD the value from the originating field to the destination field. If you want the destination field to be emptied first, you can use the "Clear Field Value" first to clear it.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

Looking for anyone who made the switch to Data Center

The Jira Marketing team is putting together an ebook on migrating to Data Center. We're looking for pro tips on how you staffed your project team and organized your Proof of Concept. Share yo...

29 views 0 2
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you