Changing working time

Helmuth Santos July 13, 2014

I am using JIRA ondemand.

If due time is 5pm and beyond, it is considered due on the next day. For example, if an issue is due at 5pm today, it will appear on the calendar as due tomorrow.

What setting should I change so that all issues due today (up to 12midnight) will be considered as due today?

I tried changing the tracking time from 8 to 24 but it doesn't have an effect.

1 answer

1 accepted

1 vote
Answer accepted
Diego Zarpelon
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
July 15, 2014

Hello Helmuth

For that you can configure the workday hours as described here, basically the process is to change the "hours per day" tp something like 24 or any number of hours you want

Hope this helps and let me know if there's something else I can help you.
Best regards.
Diego Zarpelon
Atlassian JIRA Support Engineer

Helmuth Santos July 15, 2014

Hi Diego,

I've changed the workday just like you advised and it helped.

Our server timezone was also wrong and had an effect on the issue I raised. This has been corrected also.

Thanks for the help,

Helmuth

Diego Zarpelon
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
July 15, 2014

Hey Helmuth

Great to hear that I could've managed to help you!

Let me know if I can be of any other help.