Can not close sprint - admin perms needed in second project

I have a users getting an error message everytime they try to close a sprint.

ERROR:

To update this sprint you must have Project Administrator permissions for all of the following projects: Project A, Project B.

The sprint he is trying to close is in Project B. There are no Project A issues in the Project B sprint. There are no Project B issue in Project A.

2 answers

1 accepted

Accepted Answer
0 votes

You've defined a sprint that crosses both projects A and B. So you need to be admin to close it. It doesn't matter if one of the projects doesn't have any issues in that particular sprint, the problem is that it *might* have issues in the sprint, so you need to be admin before you have the right to close it.

How do you define a sprint to cross multiple projects?

Create a scrum board that crosses multiple projects. You should find you have a filter with the same name as the board, which just says "project = (A,B) order by rank asc"

Can you get the JQL used for the filter for the board?

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 18, 2018 in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

25,066 views 2 7
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you