Hi guys,
I´m having some issues tracking my Sprint progress. My current configuration is as follows:
- A custom field as a Select List (single choice) for my Story Points (1,2,3,5,8,13).
- Selected Story Points as the field to track progress on the sprint. However, my Sprint burndown looks flat, no data visible.
What am I doing wrong? I think the values on my dropdown are probably not considered numeric, but I´m unsure what to do next to fix it.
I appreciate any help you can provide.
Hello @Olivia Medina
Welcome to the community.
Story Points is the name of a built-in field. You should generally not create a custom field with the same name as an existing field. That leads to confusion as you don't really know which of those fields you have selected.
In my environment I created a new custom field "New Story Points Selection List", like yours. When I go to the Board Settings > Estimation, that field is not available to select.
Based on that I would say that when you selected "Story Points" for your board, you actually selected the original built-in Story Points field, which you are not actually using for your data. That is why the progress shows no data.
And, Estimation Statistic has to be a Number type of field. You can't use a Selection List type of field, as Jira is not designed to decipher if the available values are text or numbers.