Burndown chart error

Krisna Leo Parista
Contributor
July 23, 2021

Hello ! I am a newbie here, would somebody please help me?

I am using story point estimate for the active sprint (1,2,3,5,8,13,21 story points) and based on rough calculation the total of this sprint should be at around 200SP.
Today is day 5 out of 10 working days.

I am checking my burndown chart, but why does it show flat like this? 
Slide2.JPG

however, the issues counted graph is shown but without guideline:

Slide3.JPG

This is the detail of the ticketing:

Slide4.JPG

Appreciate for your help! Thank you.

Cheers,
Krisna

2 answers

2 accepted

1 vote
Answer accepted
Alex Koxaras _Relational_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
July 23, 2021

Hi @Krisna Leo Parista

In the burndown chart you have selected the "Story Point" selection, but on the issue you've populated the field "Story Point Estimate", which is a different. Field. Try to populate the "Story Point" field and run the report again. That ought to do the trick.

Regards,
Alex

Krisna Leo Parista
Contributor
July 23, 2021

Hi Alex, 

It's krisna again here :) I did it, yay, thank you to airbus & you for the help!
Somehow the guideline doesn't show... but it's fine, I need the story points line more. Burndown chart issue.jpg 


Cheers,
Krisna

1 vote
Answer accepted
Airbus Driver
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 23, 2021

Are you using a team-managed project or a company-managed project? You'll find this on the lower left hand side of your Jira page.

If you're using a company-managed project, the correct field should be Story Points

If you're using a team-managed project, the correct field should be Story Point Estimate

I have a feeling you might using the wrong field.

Krisna Leo Parista
Contributor
July 23, 2021

Thank you for your reply ! 

Ahhh I see, yes I am using company-manage project .
Do you know how to change story points estimate ----> story points? 

In the ticket box it has only 3 options :
- story points estimate
- original estimate
- time tracking

no story points :(

I just googled on another post let me try this now:

  1. Select the Jira icon > Jira settings > Issues.
  2. Under FIELDS, select Custom Fields.
  3. Find the Story Points Field and note the Issue type(s) that are associated with it.
  4. To allow Tasks (or Bugs) to use Story Points open the three dot menu and select "Configure".
  5. Under the heading "Default Configuration Scheme for Story Points" select "Edit Configuration".
  6. Finally, find the heading "Choose applicable issue types" and select the Issue "Task" issue type is selected (along with Stories and Epics).

i'll get back here soon if this works.

Cheers,
Krisna
 

Like Airbus Driver likes this
Krisna Leo Parista
Contributor
July 23, 2021

Hello Airbus Driver,

I did it! Thank you for your help .. I've already voted & accepted your answer :)

Cheers,
Krisna

Like Airbus Driver likes this

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events