Burndown chart effect for differed tasks Edited

I have a column in my Jira board as differed. Developers can move sub tasks into differ status without entering time. Deffer state means that developer will not be attended to the sub task.

When a sub task is moved to differed state the burndown chart is not get updated. When to add time to the sub task and move it to differed burndown chart gets updated, which is invalid in my scenario. 

How can I get burndown chart updated once I differ a sub task?

1 answer

0 votes

You won't get sub-tasks to update a burn-down chart.  Burn down measures delivery against commitment, and you do not commit to sub-tasks, only thier parents.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted in Jira

Demo Den Ep. 7: New Jira Cloud Reports

Learn how to use two new reports for next-gen projects in Jira Cloud:  Cumulative flow diagram and Sprint burndown chart. Ivan Teong, Product Manager, Jira Software, demos the Cumulative ...

314 views 1 3
Join discussion

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you