Burndown Chart without using Story point

kay October 28, 2019

Hi everyone, 

Our team decided not to use Story point. Nevertheless, our team would like to have a Burndown chart.

Do you perhaps know how we can have a burndown chart without story point ? 

( e.g. By the tasks that we´re working on., Progress, Stuck, done...  ) 

We´re using  server version 

2 answers

1 accepted

0 votes
Answer accepted
Ollie Guan
Community Champion
October 28, 2019

Hello @kay .

A Burndown Chart shows the actual and estimated amount of work to be done in a sprint. The horizontal x-axis in a Burndown Chart indicates time, and the vertical y-axis indicates cards (issues).

The vertical axis represents the estimation statistic that you have configured for your board.

https://confluence.atlassian.com/display/JIRASOFTWARESERVER083/Burndown+Chart

QQ截图20191028215722.png

kay October 29, 2019

Thanks for your Answer :) 

It was helpful !

1 vote
Jack Brickey
Community Champion
October 28, 2019

you can use burndown w/ time estimate. Board settings > Estimation > Original Time Estimate