Now I got 4 columns which are “To Do”, “In Progress”, “In Review”, “Done” from left to right.
Following current rules now, the points of each task will be deducted once moving to the most-right column.
Can I change any setting to let the points be deducted if I move the cards to “In Review” column (the 3rd column from the left side)?
Thanks if anyone can answer my question!
Hi @Tracy Liu ,
An issue is considered to be 'Done' when it is in a status that has been mapped to the right-most column of your board.
I think in the your case, when Issue appears in the "In Review" column, it is impossible to calculate the number of burndown points.
So if i need an issue is considered to be 'Done', it must satisfied double conditions, right?
It means an issue should be dragged to the right-most column and also tagged as 'Done' or 'Resolved' for its status.
That is an issue wont't be considered to be 'Done' even i tagged it as 'Done' or 'Resolved' but it's not in the right-most column.
Do i understand correctly?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes, the single right-most column will always be green, representing items in a 'successful' state.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.