The previous sprint has been closed and is showing data in reports. The next sprint has the available 'Start Sprint' button, but when clicking it, it displays an error saying another sprint is 'active' currently.
Hello @Joel Durham
Welcome to the community.
Can you make sure that you don't have an another board that include a sprint with issue that appear in your backlog.
Do you have the feature parallel sprints enable ?
I do not have that enabled; i think possibly renaming sprints could have affected something across two projects.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
verify that indeed no sprints are open using this JQL - project = myproject and and Sprint in openSprints(). Replace myproject with the project(s) associated w/ you board. Are any issues returned?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.