Adding a a defect to an active sprint change the scope? How to avoid changing the scope

 

1 answer

0 votes

You don't.  If you are adding things to a sprint, you're changing the scope.  JIRA Software recognises and reports on that.

It means you are not supposed to add a defect to a current sprint which is active???

Correct.  The very definition of "scope change" is "you add things you did not originally plan for into the sprint".

You either accept that you are changing the sprint or leave it for the next sprint!

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Jan 08, 2019 in Jira

How to Jira for designers

I’m a designer on the Jira team. For a long time, I’ve fielded questions from other designers about how they should be using Jira Software with their design team. I’ve also heard feedback from other ...

884 views 3 9
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you