Adding a a defect to an active sprint change the scope? How to avoid changing the scope

 

1 answer

0 votes

You don't.  If you are adding things to a sprint, you're changing the scope.  JIRA Software recognises and reports on that.

It means you are not supposed to add a defect to a current sprint which is active???

Correct.  The very definition of "scope change" is "you add things you did not originally plan for into the sprint".

You either accept that you are changing the sprint or leave it for the next sprint!

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 18, 2018 in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

26,872 views 2 7
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you