Is it possible to add the Sub-Task Original estimate in Parent Task?

Mohammed Anwar Shaikh
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 22, 2021

Hi,
Is it possible to add the Original Estimate of Sub Task in the Parent Task?

I have multiple sub tasks for each parent task and would like to add the sub-tasks original estimate to be get added in the Parent task.

I tried Automation, but didn't got any success. 

Any idea, is it possible in Jira Work Management?

Regards,
Anwar Shaikh

2 answers

1 vote
Curt Holley
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
December 22, 2021

All you need do to get sub-tasks original estimate and time tracking to sum-up into their parent story is....use the original estimate (and time tracking) of the sub-tasks. The story will show the progress in the time tracking section. Note: it doesn't ever populate the original estimate field (though automation inspired by @Fabian Lim link could be used to achieve that, if need be.

In the below example (screenshot of the parent story) I have added 1d original estimates to 2 sub-tasks and recorded 1h in the time tracking of one of those sub-tasks. Jira is summing the estimates and subtracting the effort on the story. Note: ensure the "include sub-tasks" checkbox is ticked.

time2.png

0 votes
Fabian Lim
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
December 22, 2021

Hi @Mohammed Anwar Shaikh

Take a look at this video tutorial where you can switch story points to original estimate: https://youtu.be/PROcxEOMyGM

Regards