The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

why is my scrum board not showing tasks encompassed within a story?

Aston Martin
Contributor
December 13, 2013

This is the view on Rally software, and the later image is from JIRA. I would like to view the tasks grouped by stories as in Rally, and not just as a list of tasks. Please let me know the configuration to be done. Thanks in advance.

Rally View

JIRA View

2 answers

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
Aston Martin
Contributor
January 23, 2014

Though I have added a new column, I did not map the statuses

Please see "3) Create a new column and map it to the new Status" here:

https://confluence.atlassian.com/display/AGILE/Tutorial+-+Adding+a+Column+to+a+Board

0 votes
Dobroslawa Wierzbicka
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
December 15, 2013

Seems like what you're looking for is swimlanes based on Stories. To set them up, go to Board > Configure > Swimlanes and pick "Stories" from the dropdown. Note that this will work only if you use sub-tasks in your stories; from the screenshot you've provided, I can't tell if that's the case.