when a issue has multiple components which lead will be issue assignee ?
@Syave Srikanth Hahaha It is one of the confusing topics, let me try to explain it
Components are assigned in the order :- Component Lead >> Project Lead >> Unassigned >> Project default
If an issue has multiple components, and at least one of them uses Component Lead, then the Component Lead takes precedence over Project Lead, Project Default, and Unassignedas the Assignee. If the components have different Component Leads, the default assignee will be set to the Component Lead of the component that is first alphabetically.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
👋 Hi there Jira Community! A few months ago we shared with you plans around renaming epics in your company-managed projects. As part of these changes, we highlighted upcoming changes to epics on...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.