Hi Team,
We have issue with the ELN next Gen project sprint report.
I see that none of the user stories we had are completed - even they are done.
Please see in the image snip below:
Regards,
Anuradha
Hi, on Jira which defines is a task is done or not is not the status name either the status colour but the Resolution field.
Please ensure that Resolution field is set when reached a final status either manually or automatically using a postfunction within the workflow.
Further information can be found at :
https://confluence.atlassian.com/cloudkb/best-practices-on-using-the-resolution-field-968660796.html
Regards
ups... true that. I thought this was an agile board related question. Upvoted
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Looking at the upper left corner of the image you provided, the board is associated with a Classic Software Project, not a Next Gen project.
In that case, as @Jack Nolddor _Sweet Bananas_ said, the report is looking at the Resolution field to determine if the issue is completed, not just the Status field.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.