Hi
I have several stories that have all subtasks completed and status of story is verified/closed yet they are not allowing me to close the sprint. Does it matter if linked issues are still open
Linked issues are irrelevant (unless you've set up some form of validation which would prevent the main story moving to "done")
For a story to be "done", it, and all of its subtasks must be in the last column on the board when you close the sprint.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The label is irrelevant. What matters is the column they are in (which is determined by their status)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please see attached - I am not seeing the subtasks on the board and Story is in Verified and SUB TASKS are also completed - but still not allowing me to close Sprint.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Catch up with Atlassian Product Managers in our 2020 Demo Den round-up! From Advanced Roadmaps to Code in Jira to Next-Gen Workflows, check out the videos below to help up-level your work in the new ...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.