Where do I find the info "resolved during sprint #..."

Charles Delaporte September 9, 2018

Hi,

 

When a issue is resolved during a sprint, is the corresponding sprint number stored in a specific field?

 

Thanks

1 answer

0 votes
Jack Brickey
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
September 9, 2018

The Sprint field is updated w/ the sprint value as soon as the issue is added to the sprint. It is not when the issue is completed. In fact if an issue in a sprint is not completed in the sprint then the sprint values will accumulate. For example, let's say that an issue is first assigned to Sprint1 and not completed and then Sprint2 and not complete but finally is completed in Sprint3 then the value in the Sprint field for this issue will be "Sprint1, Sprint2, Sprint". Unless of course the field is edited to remove the previous sprints.

Suggest an answer

Log in or Sign up to answer