We are logging actual time spent for each Story. When I click the story I can see under Time Tracking "Estimated" says not specified. I'd like to enter our original estimates here, and I can't figure out where to edit this. Screenshot attached.
FireShot Capture 211 - [PLAKTHAT-20] Remove Shar_ - https___mystyle.atlassian.net_browse_PLAKTHAT-20.png
As an admin, can you have a look at the "screens" for Create and Edit? I suspect they are missing the field "time tracking", which will give you access to enter and update estimates.