When creating a sprint in project A, the sprint also shows up in project B.

Quinten Rutgers December 2, 2019

After moving 1 user story from project B to project A, it now happens to be so that when I create a sprint in project A, it also appears in project B (but not the other way around). I cannot find anywhere why this is happening nor how I can undo this. 

Any advice would be appreciated greatly, thanks in advance!

1 answer

1 vote
Dar Kronenblum
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 2, 2019

Hi @Quinten Rutgers 

sprint is based on board and not on project

you should check the filter defined in each board configuration- if each filter is include only the specific project the behavior you mentioned should not happen

if there is at least one issue in the board A that is assigned to sprint B sprint B will appear in board A

 

hope that helps,

Dar