After moving 1 user story from project B to project A, it now happens to be so that when I create a sprint in project A, it also appears in project B (but not the other way around). I cannot find anywhere why this is happening nor how I can undo this.
Any advice would be appreciated greatly, thanks in advance!
sprint is based on board and not on project
you should check the filter defined in each board configuration- if each filter is include only the specific project the behavior you mentioned should not happen
if there is at least one issue in the board A that is assigned to sprint B sprint B will appear in board A
hope that helps,
Dar