I have the below set of Epic workflow statuses, (All global status)
Backlog -> Pre- Planning > Planning > Ready & Planned > Working > Delivered
So, when an Epic issue moves up from ' Working' to any other status above (like, Ready & Planned, Planning , Backlog), all stories associated with the Epic, which are in 'Working' status should be moved to 'To-do', except for the Done stories which are already completed.
How to enable this setup the workflows & which workflow - Epic or Story ?
Thank you
You should consider using automation for this not post function.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Jack Brickey Thank you for the comment. At the moment, able to achieve this using Automation. But also looking at the possibility of using Scriptrunner.