You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
What is the number of 'Overall sprint progress bar' in Sprint Health gadget ?
As you know, there are numbers over the 'Overall sprint progress bar' in Sprint Health gadget.
- Normally
1) Blue : "To Do" & numbers (4)
2) Yellow : "In Progress" & Numbers (9)
3) Green : "Done/Closed" & Numbers (2)
I thought those(4,9,2) were the story points, but sometimes the number is different from when I follow the link of "Issue Navigator".
For example, I followed the link of "2"(green) to "Issue Navigator" and I sum all story points, "34.95". It's different between the number green area (2) in Overall sprint progress and the number of sum (34.95) following link of "Issue Navigator"
I don't know why the number is different between 'Overall sprint progress' number and issue navigator number (Sum of story points of issues)
Please give me an advice.
Sincerely,
Tim
I figure out the reason.
Our project team has 2 scrum board but we're using 1 same sprint.
- So in the 'Sprint Health Gadget' that's correct number (ToDo : 4, InProgress: 9, Done: 2)
But when I click the link "View in Issue Navigator" as below picture, the JQL is not same as the board filter query.
So it's the main reason is the difference is to use the same sprint at the different board.
It's posted as follows,
Thank you for viewing my question.