The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results forĀ 
Search instead forĀ 
Did you mean:Ā 

Using automation to move epics to the next status, according to movement of sub tasks.

Billy Macrae
Contributor
October 28, 2022

Hi there.

Can someone help me with the correct automation formula for this please?

When I move a sub-task, development task or bug (all of which sit below an epic in our proiject), into "In development" status, I would like the epic they sit within to move accordingly, into "In Dev" status.

Below if the rule I'm currently using, which is clearly wrong.

Any help hugely appreciated.

Thank you. :)

Getting epics to move to In Dev.png

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

2 votes
Answer accepted
Mikael Sandberg
Community Champion
October 28, 2022

You need to change your branch to be the one For Epic (parent) that you can find if you go to the Automation library.

Screenshot 2022-10-28 at 7.10.14 AM.png