User can´t add correct future sprint to ticket

Erik Ekengren October 29, 2020

Hi! 

I have a headscratcher to a problem that I would need help with. I have created a scrum board with several sprints, 1 active and 5 future sprints. I would like to add one specific ticket to the fifth future sprint, and I as a Jira admin are able to do it however when another user try to do it he will only see the first 3 future sprints but not the 2 last one in that board. When he tries to add a sprint in the sprint field he can only see the active sprint and the first 3 sprints and he is not able to search for it. 

Anyone that has an idea why I am able to do this and he is not? 

1 answer

1 accepted

0 votes
Answer accepted
Erik Ekengren October 30, 2020

Apparently the issue will be solved if the user go to the backlog of the specific board which have all the sprints. Then he/she will be able to select the sprints directly from the issues. A re-indexing of Jira doesn´t resolve this though...

Vitaliy Darda November 19, 2020

Hi Eric
I have faced same issue on Jira Server 8.13, have you fired a bug to Atl team?

Erik Ekengren November 19, 2020

Hi Vitaliy!

I never did, but since you also have the same problem it must be a bug. Therefore I just created a bug report and will get back to you when I get a response from Atlassian.

BR/

Erik

Vitaliy Darda November 19, 2020

I have found some https://jira.atlassian.com/browse/JSWSERVER-20679
from Server 8.11 maybe there are other related bugs already. Anyway thank you.

Erik Ekengren November 19, 2020

Thank you! Seems like an upgrade to new version will solve it then :) 

Samantha Adrichem June 30, 2021

For people finding this,

This issue still persists in v 8.12.1 you need to upgrade to 8.13.1 or 8.14.0